Dickerson Place

Dickerson Place

Dickerson Place is property located in Colwood, BC. MSR was contacted by the owners of the property to provide engineering consultation for the subdivision of their property into two separate lots. MSR will help with the investigation of and upgrades to the existing wastewater treatment system as well as provide a design for the new wastewater treatment system required for the new home. MSR is also coordinating with the City of Colwood for the subdivision process and the required servicing for each lots.

Matt Gable, the project designer and drafting designer, has gone out to site to investigate the property’s soil characteristics by conducting test pits and percolation tests. He has also determined the configuration and capacity of the existing wastewater system and appropriate upgrades that need to be implemented to the system. The City of Colwood issued the Preliminary Layout Assessment (PLA) for the subdivision. MSR Solutions has responded with our proposal for the civil works included in the lot frontage works. We are currently waiting on the review of our proposal by the City of Colwood.

Cottages on Osoyoos Lake, Oliver, BC

Cottages on Osoyoos Lake, Oliver, BC

Cottages on Osoyoos Lake is a 300-home residential development on Osoyoos Lake.

We were retained to design a water treatment plant and wastewater treatment plant co-housed in a single treatment building and obtained approval from Aboriginal Affairs and Northern Development Canada (AANDC). Wastewater works include screening, equalization, chemical nutrient removal and flat plate membranes from WesTech Engineering. Discharge is to rapid infiltration basins and subsurface drip irrigation. We provided construction oversight and commissioning support.

We continue to provide ongoing operation support.

See our Wastewater Treatment Services page for more information on what MSR Solutions can do for you.

Port Renfrew CRD – Water System Upgrades

Port Renfrew CRD – Water System Upgrades

An ongoing project to upgrade the capacity of the water system in Port Renfrew, BC to allow for continued growth within the community.

The first phase of the Port Renfrew project involved upgrading the well pump, booster pumps and the associated piping and controls in order to increase the water supply available to the town. The second phase will involve upgrades to the town’s storage capacity by adding a second reservoir, providing increased water supply for fire protection and emergency storage.